| Pre termite treatment for commercial and residential
|
Foundation on ground level.
The Chemicals used for the soil treatment shall be as follows;
1. Site Clearance:
The site under reference must have been cleaned as to remove all wood waste and other unwanted waste material. Special note should be taken, to remove buried tree trunks and branches, any wooden pieces which are likely to remain under the ground to avoid any possibility of termite colonization.
2. Treaments of foundation:
When the foundation trenches are ready and before putting down the ballast, the floors of foundation trenches are to be bored with a screw bar at specific distance. The anti-termite emulsion should be then sprayed over the floor as per the standard rates viz, 7 liter per Sq.ft.
3.Treatments of Backfill earth: Anti Termite emulsion spraying is done when the foundation walls are ready above ground level and the earth is being filled back in the gaps & sides, after every layer of earth of approximately I ft. This evidently completes the treatment for foundation internally as well as externally so as create Anti Termite chemical barrier.
4. Treatments of Plinth Area The entire plinth area is to be treated prior to commencing the floor work. This is done by similarly by boring the floor area at intervals of one foot (60 cms) with a screw bar and then spraying the Anti Termite emulsion at the prescribed rate.
|

|
|
|